The Royal Bridges in Piła

Construction of bridge structures along the Piła bypass: three-span bridge MG 1 at km 2+708.54, four-span viaduct EG 2 at km 2+867.30,
single-span bridge MG 3 at km 3+000.81.

INVESTOR:

Urząd Miasta Piły

CONTRACTOR:

POL-DRÓG Piła (w konsorcjum z POL-DRÓG Wałcz i Firmą
„GOTOWSKI” Budownictwo Komunikacyjne i Przemysłowe Sp. z o.o.)

INVESTMENT COST:

43 114 811 PLN

LENGHT/SURFACE AREA:

1 742 mb

Scope

BRIDGE CONSTRUCTION

  • Three-span bridge MG 1 with a length of 84.0 m:
The load-bearing structure is a composite construction consisting of 6 steel girders with variable heights, connected with a reinforced concrete slab.
  • Four-span viaduct EG 2 with a length of 70.00 m: continuous reinforced concrete slab structure.
  • Single-span bridge MG 3 with a length of 32.0 m:
two-girder prestressed concrete structure with
a structural height of 0.90 m.